Plant Area Redevelopment Progress

Check out the progress of the new Plant Area redevelopment.

Every week we will bring you photos and details of the construction.

Click on a thunbnail to see the larger image.

Week One

The Poly Tunnels have been taken down and the Plant Area has been cleared.

Work has commenced on the footings.

Week Two

The footings have been completed and installation of the uprights has begun.

Week Three

Continuation of the uprights installation.

Please note: The sun has made an apperance!

Week Four

The cross bracing is now going up.

Week Five

The guttering in the new plant area is being installed.

Week Six

Real progress was made this week,  the roof supports are all in place.

And a third of the new roof has been installed, its all looking good for completion on the 1st March.

Week Seven

Again good progress was made this week,  the roof is completed.

Installation of the lighting and drainage begins, and the testing of the roof also took place.

Week Eight

The last week!

All the lighting and drainage has been completed and now the finishing touches are being applied.

The side screens are going up and all looks good for completion this Thursday 4th March.

Three days later than planned, but still great considering the weather we have had.

 

So we will finally have our new all weather roof, by the end of this week.  So why not come to Waterside and see for yourself the difference and the impact this new development has made.

Woopee

Garden Club Login




Login reminder Forgot login?
Register Register

 

 

 

 

 

 

 

Opening Hours:

Monday to Saturday
9am - 5.30pm
Sunday
10.30am - 4.30pm
Bank Holiday Mondays
9am - 5.30pm

 

Weather Forecast:

Cloudy Few Showers Mostly Cloudy Partly Cloudy Partly Cloudy
3ºC 7ºC 9ºC 9ºC 9ºC
Fri Sat Sun Mon Tue

Contact Us:

Waterside Garden Centre
King Street, Baston
Peterborough, PE6 9NY.
Tel. 01778 560000